Ultra-large intelligent automated warehouse (under construction) project – a 20,000+ cargo space all-steel structure warehousing hub.

A leading domestic FMCG distribution enterprise, serving over 100,000 terminal stores in more than 30 provinces and cities with an annual distribution scale of over 5 billion yuan, needs to build a regional intelligent warehousing hub to support logistics turnover after business expansion.

Ultra-large intelligent automated warehouse (under construction) project – a 20,000+ cargo space all-steel structure warehousing hub.
Project Background

The existing warehousing network has saturated space, and the daily manual sorting capacity is less than 8,000 orders, which cannot meet the 10,000+ daily order demand after business growth; meanwhile, multi-category FMCGs (daily chemicals, food) have large storage specification differences, and the space utilization rate of traditional flat warehouses is less than 30%, so a new super-large intelligent stereoscopic warehouse is urgently needed to realize high-density storage and automated operations.

Solution
  1. Structural construction: Adopt factory-prefabricated shelf modules + on-site laser positioning hoisting, control the installation error of a single shelf group within ±3mm, and ensure structural bearing and equipment adaptability.

  2. Schedule management: Implement a parallel construction plan for separate aisles, plan tower crane operation paths through an intelligent scheduling system, and achieve over 50 shelf modules hoisted per day.

  3. Equipment reservation: Cooperate with automated equipment suppliers to intervene in shelf design in advance, reserve stacker crane track slots and conveyor line connection ports, and ensure zero adaptation cost for later equipment installation.


Project Difficulties
  1. The 22-meter-high steel structure shelves require strict hoisting precision to ensure overall structural stability and equipment connection compatibility.

  2. The project duration is only 120 days, and 3 large tower cranes need to be coordinated for simultaneous operation to avoid construction cross-interference.

  3. It needs to connect automated equipment such as stacker cranes and conveyor lines in the later stage, so the early shelf layout needs to reserve millimeter-level interfaces.


Project Value
  1. Space expansion: 20,000+ storage positions, space utilization rate increased to 85%, supporting 3 years of business expansion needs.

  2. Efficiency improvement: After connecting automated equipment in the later stage, the daily order processing capacity will increase to 20,000 orders, and the sorting efficiency will increase by 150%.

  3. Cost optimization: Modular construction reduces construction costs by 6%, and advance interface reservation reduces later equipment adaptation costs by over 200,000 yuan.